Photo courtesy of AvalonBay Communities
Located in the Historic North Andover Mill neighborhood, this residential development offers 221 one-to-three-bedroom apartment homes for lease. The structures are slab on grade wood frame construction with NFPA13 fire suppression systems, plus brick and Hardie/vinyl exteriors. With designs inspired by the area’s historic mills, the project features three multifamily residential buildings and a stand-alone clubhouse.
The $55-million, two-year project was completed under budget and on schedule in May. The three residential buildings are garden style mid-rise buildings, two containing 85 units and one containing 51. Amenities include an outdoor pool and outdoor kitchen.
Major permitting and construction challenges arose from the onset. Two high-tension 23-kVA overhead power lines that feed more than 1 million National Grid customers sat just 25 ft above ground, running down the center of the site to split it in two.
Photo courtesy of AvalonBay Communities
To bring these out of the sky, the contractor installed an underground ductbank consisting of 20 5-in. pipes following the overhead line’s pathway. Once the duct bank was complete, remaining sitework and building construction began.
Utility relocations took place over two months as the team worked together with National Grid to re-feed their overhead wires underground and remove overhead infrastructure to make way for construction. Due to the complicated nature of the site, ground improvements were also necessary. The geotechnical engineer chose rapid impact compaction as the least invasive method to achieve proper soil bearing strength. A rapid impact hammer compacted the building pads over 10 days.
Heavy sitework was completed by early fall with the first course of asphalt down by October to allow for a smooth transition into framing. Over the course of 97,649 worker hours, with more than 100 workers onsite on an average day, the team had no recordable injuries or lost time.
The project team performed a thorough safety prequalification process with each contractor brought on site.
Trade partners were contractually obligated to meet minimum safety requirements, while the project’s safety professional captured all external safety observations in I-BEAM, allowing for data analysis to influence goals, training and planning. Crews also implemented an existing fire elimination and security program for wood frame construction. Elements included the MFIRE spray fire inhibitor, temperature sensors, surveillance cameras and adherence to a project-specific Nayion Fire Protection Association 241 written plan.
Photo courtesy of AvalonBay Communities
In 2022, the project team expanded its safety efforts by recognizing potential stresses that can be attributed to exclusion, unconscious bias, harassment and their impacts on individual mental health and physical safety. The team communicated this message by placing language that requires and promotes an inclusive workplace into contracts, training orientations and site signage. The team participated in two Culture of Care stand-downs and an Inclusion Week stand-down.

ENR Subscribe
 
 

You must have JavaScript enabled to enjoy a limited number of articles over the next 30 days.

Top Design FirmsTop Design Firms
New York and New England Designers Eclipse Pre-pandemic Revenue in 2022
Top ContractorsTop Contractors
Project Diversification Sustains Northeast Contractors
Top Specialty ContractorsTop Specialty Contractors
Northeast Specialty FIrms Face Economic Shifts Headfirst
Industry Jobs

ENR UNLIMITED
Copyright ©2023. All Rights Reserved BNP Media.
Design, CMS, Hosting & Web Development :: ePublishing

source