Independent power producer Alinta Energy expects work on a 45 MW solar farm and 35 MW/35 MWh battery energy storage system planned for Western Australia’s Pilbara region will commence inside two months following the appointment of contractors to construct and connect the hybrid project.
Image: Alinta Energy
Alinta Energy has awarded the engineering, procurement and construction (EPC) contracts for its $180 million Port Hedland Solar Battery Hybrid project which will see an initial 45 MW solar farm and 35 MW, one-hour battery energy storage system installed alongside its existing gas-fired power station site near Port Hedland on Western Australia’s north coast.
Engineering firm UGL, part of the Sydney-headquartered Cimic Group, has been appointed to deliver the battery energy storage system while SEPD Monford, a collaboration between Chinese engineering firm Shanghai Electric Power Design Institute and Perth-based construction specialist Monford Group, will deliver the solar component.
The solar farm will comprise an estimated 100,000 PV panels to be installed on a 100-hectare site about 500 metres east of Alinta’s existing gas-fired Port Hedland Power Station, located about 14 kilometres southwest of the Pilbara tow. The battery will be built adjacent to the existing power station.
Alinta said it expects contractors will be on site from July with the facility predicted to be operational by late 2024.
“We’re excited to bring these EPC partners on board to help us deliver the project for BHP and look forward to a safe and successful construction phase,” Alinta Chief Development Officer Ken Woolley said.
The large-scale solar and battery hybrid project underpins a power purchase agreement with BHP that’s expected to halve emissions from the generation of electricity used to power the mining giant’s iron ore port facilities in Port Hedland.
Once completed, the solar farm is expected to supply 100% of the average daytime energy requirements for BHP’s iron-ore operations in Port Hedland, with the remaining power requirements to be met through the integrated battery system and Alinta’s existing gas-fuelled power station.
The 45 MW solar farm and 35 MW battery is expected to form the foundation for a much larger renewable energy generation and storage facility at Port Hedland with Alinta having already secured development approvals for the sites that could facilitate a future expansion to a 60 MW two-hour battery storage system and 90 MW solar array.
Alinta’s strategy is to use the new solar farm and the big battery to respond to demand from its corporate customers for cleaner energy.
Image: WorkPac
The appointment of EPC contractors for the Port Hedland project comes as Alinta continues to assess the sell-down of its WA operations.
The Sydney-headquartered company, owned by Hong Kong-based Chow Tai Fook Enterprises, is reportedly seeking to offload an 80% stake in its generation and transmission assets in WA with bankers Goldman Sachs appointed to oversee the transaction.
Alinta’s Pilbara assets include the existing Port Hedland Power Station, the 60 MW Chichester Solar Farm, and the 178 MW dual fuel (gas and distillate) Newman Power Station and associated 35 MW/11 MWh battery energy storage system. Alinta also owns and operates transmission infrastructure in the region including high-voltage power lines and gas pipelines.
It is expected a formal auction for the assets will be launched later this year.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
More articles from David Carroll
Please be mindful of our community standards.
Your email address will not be published. Required fields are marked *







By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.
Legal Notice Terms and Conditions Privacy Policy © pv magazine 2023
pv magazine Australia offers bi-weekly updates of the latest photovoltaics news.
We also offer comprehensive global coverage of the most important solar markets worldwide. Select one or more editions for targeted, up to date information delivered straight to your inbox.
This website uses cookies to anonymously count visitor numbers. To find out more, please see our Data Protection Policy.
The cookie settings on this website are set to “allow cookies” to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click “Accept” below then you are consenting to this.
Close

source